2
0
My second qustion for the day

Is there possible to get primavera spotlight function in MSP?

Regards

Dan

3 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Dan,
    spotlight does not exist in MSP
    you could use the Task Range or Date Range filters instead, but it is not as useful as the spotlight
    many P3 and P6 functionalities do not exist in MSP
    Alexandre
  2. 0
    Dan Mårtensson ·
    Hello Alexander,

    Yes I know and it is a very god function that are missing in msp. I thougt maybe some one hade made a macro make this work.

    //Dan
  3. 0
    Alexandre Faulx-Briole ·
    Dan,
    you could record a macro which would use both the current date and the status date (in Project, Project Information) to define the Spotlight zone
    these are the only user defined dates to be used to define an area on the screen
    Alexandre