Calendars in Microsoft Project
In the Open Standard
Lo GaryMember for 16 years 8 months
- Created
- 4
- 5
0
Dear All,
I want to set different calendars for different activities
1) Calendar 1 for normal construction activities (work week Monday to Saturday 8:00a.m. to 6:00p.m.);
2) Calendar 2 for consultant working day (Monday to Friday 9:00a.m. to 6:00p.m.);
3) Calendar 3 for contagious activities ( 24 hours e.g. concrete curing, time allowed for striking of formwork etc.)
It is then found that the start and finish date/time of the activities would be mess up. How to resolve this problem?
In addition, could I force an activity to start on the next day rather than start immediately on the remaining time of the previous day. e.g. if there is only 2 hours left on day 1 which is not adequate to pour 100m3 of concrete, could the activity be force to start on day 2.
Thank!
Gary Lo
I want to set different calendars for different activities
1) Calendar 1 for normal construction activities (work week Monday to Saturday 8:00a.m. to 6:00p.m.);
2) Calendar 2 for consultant working day (Monday to Friday 9:00a.m. to 6:00p.m.);
3) Calendar 3 for contagious activities ( 24 hours e.g. concrete curing, time allowed for striking of formwork etc.)
It is then found that the start and finish date/time of the activities would be mess up. How to resolve this problem?
In addition, could I force an activity to start on the next day rather than start immediately on the remaining time of the previous day. e.g. if there is only 2 hours left on day 1 which is not adequate to pour 100m3 of concrete, could the activity be force to start on day 2.
Thank!
Gary Lo
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?