Assignment Challenges with MS Project..A few more tips

Seyma ISBLNMember for 16 years 5 months
Created
2
4
0
Hi again,

Really in toruble with my overdue uni assignment..I would appreciate the help guys.

When I assign equipments(crane, excavator) to the project (From assign resources) it changes the project completion date

It is the same problem when I assign a regular meeting as well.

What can I do to keep the project duration same and change the project cost only when I add these cost into the project?

Thanks heaps

Seyma

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Seyma,
    Right click and select task information or double click the activity. Click Advance tab and un-tick effort driven before adding new resource and your duration should not move.
  2. 0
    Seyma ISBLN ·
    Thanks for the help Rodel.Much appreciated!