Assignment Challenges with MS Project..A few more tips
In the Open Standard
Seyma ISBLNMember for 16 years 5 months
- Created
- 2
- 4
0
Hi again,
Really in toruble with my overdue uni assignment..I would appreciate the help guys.
When I assign equipments(crane, excavator) to the project (From assign resources) it changes the project completion date
It is the same problem when I assign a regular meeting as well.
What can I do to keep the project duration same and change the project cost only when I add these cost into the project?
Thanks heaps
Seyma
Really in toruble with my overdue uni assignment..I would appreciate the help guys.
When I assign equipments(crane, excavator) to the project (From assign resources) it changes the project completion date
It is the same problem when I assign a regular meeting as well.
What can I do to keep the project duration same and change the project cost only when I add these cost into the project?
Thanks heaps
Seyma
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?