Mark in the bar view

Dan MårtenssonMember for 16 years 8 months
Created
5
3
0
Hello all,

I want to mark July in my plan as vacation with a grey field. But I still want my work left in July. So, what I want is just to make the pm aware of that some of the crew want to have there vacation.

Is this possible?

Regards

Dan

5 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Dan,
    Create a calendar that reflects all those vacation dates and assigned only to those resource that having vacation as base calendar.
  2. 0
    Dan Mårtensson ·
    Thank you Rodel!

    I wasn’t think that far :-)

    Regards

    Dan
  3. 0
    Bo Johnsen ·
    Dan,

    If you just want to make a "curtain" in your Gantt chart to show the possibility of vacation, then just make a calendar called e.g. "Possible Periods with Vacation" with the respective days marked as non-working time.

    Let all resources keep their present assigned calendars, but under "Format-Timescale-Nonworking Time (tab)" choose "Possible Periods with Vacation" in the Calendar-field. That will only have an influence on what is shown on the Gantt chart and not on any resources.

    Regards,

    Bo
  4. 0
    Dan Mårtensson ·
    It works, Thanks!

    //Dan
  5. 0
    Mike Testro ·
    Hi All

    Even within the limited scope of MSP surely the task calendar will conflict with the resource calendar.

    Which is the overide?

    Is there not an option to toggle "resource calendar as task"?

    If not why not.

    Best regards

    Mike Testro.