Swim Lanes MS Project 2003

Russ HartMember for 18 years 11 months
Created
2
3
0
A simple one for you...MS Project 2003

I’d like to show horizontal lines on the Gantt area of my schedule at summary level. I’ve checked the grid line function and "Summary Lines" is not an option.

Can anyone help?

Cheers,

Russ.

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Russ,
    Try Gridlines-> Gantt rows. You can change the interval but not selecting only summary. You can collapse to summary level if required.
  2. 0
    Rafael Davila ·
    You can create an additional custom Bar Style on top of your Summary Bar Style and use available/spare date field for the purpose of fixing a start and finish date of your line.

    Summary Line

Log in or join to reply