Iam Searching For Project sample (Cement Plant)

Yaser A. Al-BustanjiMember for 16 years 5 months
Created
2
3
0
Hi All

Iam Searching For Project sample (Cement Plant)

where can i find it
please use the private message service to make contact

2 replies

Oldest first
  1. 0
    Tamzin Morphy ·
    Do you want to base your plan on the sample? If so I wouldn’t recommend using a plan from another project. Every project is unique - different resources, environment, goals, timelines and so on.

    I always build each plan from scratch by working with my project team to:
    1. build a work breakdown structure;
    2. produce a workflow diagram;
    3. estimate effort and
    4. allocate resource.

    By all means find a sample and used it is a checklist, but don’t be tempted to skip planning with your team.

    Hope this helps.

    T Morphy
    www.planproject.co.uk
  2. 0
    Mike Testro ·
    Hi Tamzin

    Welcome to Planning Planet

    That was wise advice and in keeping with the opinions of the more experienced members of PP.

    I am looking forward to more such input.

    Best Regards

    Mike Testro