Does anyone knows how to check conflict in Ms project? im new here. Thanks in advance

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Ivy,
    Normally MS Project will not accept conflict logic and will not allow user to enter circulated loops. For some reason you manage to enter circulated loops. Try using View-> Network Diagram. It will show all the logic or relationship of all activity. You can use filter to show specific activity.