Reporting progress on a task
In the Open Standard
Shyam -=)Member for 16 years 4 months
- Created
- 3
- 4
0
All,
I have a task with a 3-day duration and I would like to report progress of 50% under its ’% complete’ column. (assume, i am on the 3rd day today). When I do this, it invariably pushes out the finish date and changes duration to a much higher no. of days .. like 10 days or more. Also, it overwrites the 50% progress I tyoed with a much lower % value in that cell. I verified that the constraint type is set as ’ASAP’. Logically I do understand that being on day 3 of a 3-day task, I should have been atleast 66% or more on the progress of the task.
Regardless, is there a way to report 50% progress on such a task and still keep the finish date unchanged?
I have a task with a 3-day duration and I would like to report progress of 50% under its ’% complete’ column. (assume, i am on the 3rd day today). When I do this, it invariably pushes out the finish date and changes duration to a much higher no. of days .. like 10 days or more. Also, it overwrites the 50% progress I tyoed with a much lower % value in that cell. I verified that the constraint type is set as ’ASAP’. Logically I do understand that being on day 3 of a 3-day task, I should have been atleast 66% or more on the progress of the task.
Regardless, is there a way to report 50% progress on such a task and still keep the finish date unchanged?
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?