Calculating Hours-Man with Project

Jhorbam Baena OrozcoMember for 17 years 1 month
Created
2
5
0
Hi...with Primavera Project Planner i can get the report of the Hours-man neccesaries to complete the project...but i not found a similar option in Microsoft Project...an option that i can use to get that information calculated by the Microsoft Project...

Can someone tell how i can get that report?...or that option are not able in Microsoft Project?

Thanks

2 replies

Oldest first
  1. 0
    Trevor Rabey ·
    Remaining Work?
    See the Work Table.
  2. 0
    Rodel Marasigan ·
    Jhorbam,
    Try View-> Task Usage or View-> Resource Usage. You can insert the column that you want to show like Baseline Work, Work, Remaining Work, Actual Work...etc. You can also apply groupings.