MSP 2003 date formart

Lan WeiMember for 16 years 1 month
Created
5
5
0
Could someone please tell me how to show start and finish dates as day 1, day 2, instead of 1/w02 etc.?

Many thanks

wei

5 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Lan,
    Tools-> Options-> Date tab then select the date format you want.
  2. 0
    Lan Wei ·
    Rodel

    Thanks but in my version of msp in tools --> options --> view there are NO day 1, day 2 format, but only 1/w09, 1/w09/01..

    I use MSP2003, what’s your version?

    wei
  3. 0
    Alexandre Faulx-Briole ·
    Lan,
    I am afraid you can’t; there is no such a date format in MS Project whatever the version is
    a workaround is to use the timescale: set up the lower level to "Days", then select the label to "D1, D2 (from start)" or "1, 2 (from start)".
    Alexandre
  4. 0
    Lan Wei ·

    Alexandre Thank you very much

    Alexandre

    Thank you very much for this.

    Do you know if you can show Day 1, day 2, etc. in P3 / P6?

  5. 0
    Alexandre Faulx-Briole ·

    Timescale

    Lan,

    yes you can!

    in P6, go to Timescale, set it up to display ordinal dates in days: it will display 1, 2, 3, ... from the selected date (project start, data date, ...)

    the same in P3, but you will have hard time to display the number on a daily basis; on my screen, it only displays the number for every monday

    Alexandre

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?