i have been created master programme in primavera p6 and i export to ms project 2007 and the programme is developed in ms project now i  need to add activity code in that but i unable to change wbs please help me to solve problem.

 

thanks

 

murali

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Mohana,there is no such

    Mohana,

    there is no such actvity codes in MS Project Standard (stand-alone) (any version) as in Primavera P6; WBS in MS Project is a calculated field you can let as build or set-up.

    you could you create a custom field to enter activity codes in it, but you will have some hard time to organize the Gantt Chart from these data.