Project Summary show only one fourth duration of activity

Kumar BaijuMember for 15 years 8 months
Created
13
5
0

Hi Alll

      I have one question about the actual duratin in MS project-2003. I am using 24 hous calander for my prject. when i updated my actual duration E.g. 10 hrs then in project summary it shows only 2.41 hrs. similiarlr when 20 hrs it appears 4.83. I cannot understand why in summary it comes only nearly one fourth duration

 

4.83 Hrs 2.41 Hrs
20 Hrs 10 Hrs

13 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hello Kumar,please check how

    Hello Kumar,

    please check how the 24h calendar is being applied in your project; I suspect this calendar was applied to subsidiary tasks (Task Information) and not to the project itself (Project Information)

    Alexandre

  2. 0
    Kumar Baiju ·

    Daer Alexandre

    Daer Alexandre

              Thanks for your reply. But i have assign in both fiel 24 hous calendar.

     

    Kumar

  3. 0
    Kumar Baiju ·

    Daer Alexandre

    Daer Alexandre

              Thanks for your reply. But i have assign in both fiel 24 hous calendar.

     

    Kumar

  4. 0
    Alexandre Faulx-Briole ·

    Well, I don't know; do you

    Well, I don't know; do you want to send me your project? I'll give you my email address in a private mesage

    Alexandre

  5. 0
    Rafael Davila ·

    Try inserting a column to

    Try inserting a column to display Task Calendar, if it differs at a Summary Bar change it to 24 hours and let us know what happened.

  6. 0
    Kumar Baiju ·

    Rafael      It does not solve

    Rafael

         It does not solve my problem

    KBJ

  7. 0
    Kumar Baiju ·

    Rafael      It does not solve

    Rafael

         It does not solve my problem

    KBJ

  8. 0
    Rafael Davila ·

    Where the calendars

    Where the calendars different?

    If different and you changed the calendar did you run a schedule run?

    I use MS Project rarely but because use MS Project 2010 I setup all task mode in automatic.

  9. 0
    Kumar Baiju ·

    Dear Rafael                In

    Dear Rafael

                   In my project Calculation mode is automatic and calendar in Task information & project infromatin is same i.e 24 hous.

     

    Regards\\

    KBJ

  10. 0
    Rafael Davila ·

    Click where you see None (at

    Click where you see None (at Summary Task) and change it to 24 hrs calendar and let me know.

  11. 0
    Kumar Baiju ·

    Dear Rafael             It is

    Dear Rafael

                It is the summary and not editable. please suggest how can i edit it.

  12. 0
    Rafael Davila ·

    You

  13. 0
    Kumar Baiju ·

    Dear Rafael          I have

    Dear Rafael

             I have seen the Video. That is for Task summry not for the Project summary. I can do also for the task summary but cannot for the project summary. If any other method you have please reply me

    Thanks\\

    KBJ