Project Summary show only one fourth duration of activity
In the Open Standard
Kumar BaijuMember for 15 years 8 months
- Created
- 13
- 5
0
Hi Alll
I have one question about the actual duratin in MS project-2003. I am using 24 hous calander for my prject. when i updated my actual duration E.g. 10 hrs then in project summary it shows only 2.41 hrs. similiarlr when 20 hrs it appears 4.83. I cannot understand why in summary it comes only nearly one fourth duration
| 4.83 Hrs | 2.41 Hrs |
| 20 Hrs | 10 Hrs |
13 replies
Oldest firstLog in or join to reply