How to update in M.S with proper way when i update some activities take dates befoe data dates

2 replies

Oldest first
  1. 0
    Ellen Lehnert, Microsoft Project MVP, PMP ·

    From the Gantt chart show the

    From the Gantt chart show the tracking table.  You will be able to enter in actual start and finish dates for a task.

  2. 0
    Amro Ahmed ·

    i know how enter these data

    i know how enter these data but after finishing update some actual dates will be before data date  cause it not work in retained logic just dates.

    my question if there is a solution  for this issue.