Cost Control MS Project 2007

Maarten van WykMember for 16 years 1 month
Created
0
3
0

Hi there,

 

I loaded the estimate into my project plan in MSP 2007 as cost and material resources. When is a cost resource used?

When I enter % complete, it also calculate my actual cost. I did untick this option but it keeps on doing it. How do I enter my actual costs for each month into the program? How do I get the program not to calculate my actual costs from the % complete, but rather enter it myself on a monthly basis.

 