Cost Control MS Project 2007
In the Open Standard
Maarten van WykMember for 16 years 1 month
- Created
- 0
- 3
0
Hi there,
I loaded the estimate into my project plan in MSP 2007 as cost and material resources. When is a cost resource used?
When I enter % complete, it also calculate my actual cost. I did untick this option but it keeps on doing it. How do I enter my actual costs for each month into the program? How do I get the program not to calculate my actual costs from the % complete, but rather enter it myself on a monthly basis.
Regards,
Maarten
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?