Cost Control MS Project 2007
In the Open Standard
Maarten van WykMember for 16 years 1 month
- Created
- 2
- 3
0
Hi there,
I loaded the estimate into my project plan in MSP 2007 as cost and material resources. When is a cost resource used?
When I enter % complete, it also calculate my actual cost. I did untick this option but it keeps on doing it. How do I enter my actual costs for each month into the program? How do I get the program not to calculate my actual costs from the % complete, but rather enter it myself on a monthly basis.
Regards,
Maarten
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?