Not transparent behavior of scheduler

Maciej GMember for 15 years 3 months
Created
1
8
0

 

I have set two tasks in automatic mode: one task after another using predecessors link as defined below. Task A is completed in 100%. 

Id |Task Name |Predecessors|Start|Finish
265|Task A|264|Fri 24/06/11|Mon 27/06/11
266|Task B|265|Fri 29/07/11|Thu 04/08/11

What I don't understand is why MS Project schedules Task B a month after the first one. I'm particularly missing feedback from MS Project justifying this decision. Without this feedback nailing down the problem and its reason becomes hard.

  1. What could be the possible reason for that?
  2. How can I get feedback from MS Project with explanation why the given task has been scheduled in a certain way?

Some more details here:

  1. Task B contrain type is "Start as soon as possible"
  2. Resources assigned to the task have no holidays in this period (no exceptions in calendar)

Thank you in advance,

Maciej

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi Maciej What was the date

    Hi Maciej

    What was the date of your progress report where you set task A at 100%?

    Best regards

    Mike Testro