MS project 2003 Duration and Finish does not reconcile
- Created
- 2
- 3
I have a strange problem, I want change my clander from 8 hrs to 9 hrs. Before doing it on the project i experimented
Created a new project put an activity
Name Duration Start Finish
Task 1 5days 11/7/11 15/7/11
Then I created a new calender with 9 hr working. Changed the calender of the task as well as default working hours of the day from 8 to 9hrs and of the week to 45 instead of 40hrs which resulted duration from 5days to 4.4days. I then changed the duration to 5 days in the duration column but the bar representing the task is finihisng on Monday week following.
Name Duration Start Finish
Task 1 5days 11/7/11 8:00 18/7/11 10:00
Please note I have changed the project calendar to new calender as well and no resourse is assigned yet.
Any help is appreciated.
Regards
Muhammad
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?