MSP 2010 wont let me baseline project
In the Open Standard
Stephen TaylorMember for 17 years 7 months
- Created
- 0
- 3
0
Hi All,
MSP 2010 will not let me set the entire project as a baseline. Ive tried it by selecting the entire project check box as well as highlighting all tasks then checking 'selected tasks'. It will let me assign a baseline if I select only a few tasks but thats it. My plan has 2500 tasks. I tired selecting 500 tasks but it wouldn't do this either.
Any ideas greatly appreciated as you can imagine this is causing me some frustration.
Cheers
Steve
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?