How can i delay my project one day

Ahmed galalMember for 15 years 2 months
Created
3
3
0

hi all,
i changed a working day to non-working day, so i need my project to respect that change to all next tasks after that day, but project made over-allocations
can anyone help me

3 replies

Oldest first
  1. 0
    Arif Khan ·

    Hi Ahmed, Just as you said, I

    Hi Ahmed,

    Just as you said, I created a Task A that starts on 1/Sep/2011 with a "Fixed Duration" of 60 days. Project automatically created the task as "Manually Schedule". I changed it to "Automatically Schedule". In the Standard Calendar (the one this project depends upon), I marked 1/Sep/2011 as a Nonworking day. Automatically Task A start date changed to 2/Sep/2011 and the Finish date also moved by one day keeping the duration same.

    Arif

  2. 0
    Kris Harry ·

    Please try rescheduling with

    Please try rescheduling with "link tasks" after selecting all tasks.

    Kris

  3. 0
    Khaja Sharief ·

    Dear Ahmed,    I suggest you

    Dear Ahmed,

        I suggest you to check whether in the project information you have kept finish date of the project. If this is done and since end date is fixed and now you change working day to non working day then logically the end date should be pushed to the next working day. Since the finish date was fixed, the project would suggest for over allocation. 