Different calender to summary task & Activitis

Mukunda YMember for 17 years 11 months
Created
2
3
0

I want to assign 6 days calender to the activities & want to calculate the summary task duration based on the 7 days calender,,, is there any way to do this,,,

 

Thanks & Regards

Mukunda

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Mukunda I don't see why

    Hi Mukunda

    I don't see why not - just create the two calendars and assign them accoringly.

    If MSP won't allow that simple operation then use real software like PowerProject.

    Best regards

    Mike Testro

  2. 0
    Mukunda Y ·

    I got it, Thank you Mike,

    I got it, Thank you Mike,