Curva S

Oreste de Souza JuniorMember for 15 years 2 months
Created
2
2
0

I wonder how best to generate an S-Curve physical progress without resource allocation. Using MS Project 2003 / 2007.
Thank you.

2 replies

Oldest first
  1. 0
    Ashik GB ·

    Hi, Can u just tell me the

    Hi,

     

    Can u just tell me the same how to do that???

  2. 0
    Donald Harrold ·

    You must assign resources to

    You must assign resources to establish a schedule that can be tracked properly