Skip to content

EV Cost and Schedule Indicators

Rohit KMember for 18 years 5 months
Created
4
6
0

Hi,

I have developed a schedule that is resource loaded with cost entered for the standard rates per hour for the respective resource. It is baseline,tracked and updated to date. In the calculation tab along with the task information for EV calculation % Complete is selected.

Now when I view the EV and EV Cost and Schedule Indicators (table - more tables), the BCWS and BCWP are indicating a value of 0, so are the various fields like SV, SV%,SPI,CV,CV%,CPI are also resulting in the value of 0.

Any suggestions to rectify this problem.

Rohit

4 replies

Oldest first
  1. 0
    Donald Harrold ·

    Are you sure you've baselined

    Are you sure you've baselined the schedule and set the progress date prior to updating progress?
  2. 0
    Rohit K ·

    yes, i have done them. my

    yes, i have done them. my case is like

    task  baseline start  baseline finish  actual start actual finish

    pcc     10.06.11     15.06.11          15.03.11   25.03.11

    like i have a new start date for my project as it was delayed and we had got new start dates, but some work ahad commenced earlier.so this might be the reason or what.

  3. 0
    Rohit K ·

    yes, i have done them. my

    yes, i have done them. my case is like

    task  baseline start  baseline finish  actual start actual finish

    pcc     10.06.11     15.06.11          15.03.11   25.03.11

    like i have a new start date for my project as it was delayed and we had got new start dates, but some work ahad commenced earlier.so this might be the reason or what.

  4. 0
    Rocky Fox ·

    And tell me how about the

    And tell me how about the values of ACWP, EAC? If they are different from 0, the reason is that you entered std. rate after saving baseline. Please check it again.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?