updating hammock task in MSP 2007

Kp RaoMember for 15 years 2 months
Created
3
3
0

Dear planners,

I am using MSP 2007.Hammock activity is not updating itself.How to set auto update of hammock task.It is like update the tasks and hammock task will be updated.

urgent help

Regards,

kp

3 replies

Oldest first
  1. 0
    Trevor Rabey ·

    Edit, Links, Update

    Edit, Links, Update

  2. 0
    Niek Zonneveld ·

    kp,You can do this but it is

    kp,

    You can do this but it is not straightforward.

    You can copy a cell in MSP and then paste the content as a link into another cell (through paste special, paste link)

    Just copying a date into the destination cell won't work because that will normally just impose a constraint and not change the duration.

    Cleaver use of formula's in combination with the above links will probably get you there, but remember MSP gets 'nervous' from these links as it keeps recalculating/updating continuously.

    H.T.H.