sheduling consective tasks with a must start directly after previous task

Alex MclellanMember for 15 years
Created
2
3
0

HI, does anyone have any fixes which would allow me to create a link or constraint which would hold two tasks together so that wherever they were scheduled they would stay together, ie if task one is scheduled for monday and lasts one day task two must start on tuesday or vice versa if task two was scheduled for a tuesday task one must be scheduled for monday. The logical sequence is obviously there but when you resource level there is nothing to group them together. I know it sounds simple but it aint

Alex

 

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Alex Use a single FS link

    Hi Alex

    Use a single FS link between Task A and B.

    Then set task A ALAP.

    If you allow the software to level your resources then it will over ride any logic that you have previously set up.

    That is why it should never be used.

    Best regards

    Mike Testro

  2. 0
    Alex Mclellan ·

    unfortunately i need to

    unfortunately i need to relevel my resources regularly. thanks anyway

    alex