Skip to content

how can define a task that last from start of project to finish of project??

Shima ZabetianMember for 15 years 6 months
Created
5
3
0

Hi, guys

I'm not good at MSP software.

how can define a task that last from start of project to finish of project??

I know that in p6, we can change the activity type to Level Of Effort, but What about MSP, how can I define this activity??

 

regards

Shima

5 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Shima Create a summary bar

    Hi Shima

    Create a summary bar over all the tasks and label it your task long activity.

    Best regards

    Mike Testro

  2. 0
    Gary Whitehead ·

    1) Set up & logically link

    1) Set up & logically link normal start & finish milestones for the start and finish of your project.

    2) Copy the Start field of your start milestone, then right click on the start field of your "level of effort" task, choose paste special > paste link

    3) Do the same with the finish date from your finish milestone

    4) Put something in the notes column explaining what you did, as the start & finish milestones won't register as predecessors of the "level of effort" task

     

     

    This is For MSP 2003. There may be a cleaner way in later versions.

     

  3. 0
    Alexandre Faulx-Briole ·

    Hello Gary,no, there is no

    Hello Gary,

    no, there is no cleaner / clever way in MSP 2007 / 2010 to build a hammock task; the way you've described is the only wy to do that

    Alexandre

  4. 0
    David Manna ·

    I agree with Mike. This

    I agree with Mike. This sounds like the best solution. I am still learning to use MSP and this forum will definitely help. 

  5. 0
    Tom Boyle ·

    The paste-links seem a bit

    The paste-links seem a bit more robust in newer versions than they were in 2003, but it's still a patchwork approach.  Past experience mostly cured me of my desire for hammocks in MSP.  Now on the few occasions I can't do without, I use alternate methods that don't give me a big headache....

    http://www.boyleprojectconsulting.com/TomsBlog/2017/09/26/an-alternate-approach-to-hammocks-in-microsoft-project/

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?