Filters in MS Project

G TMember for 15 years 9 months
Created
1
3
0

Please advise if it is possible to make the same filtering in MS project as we can do in primavera.. I mean suppose i want all acitvities that start after some date and finish no later that some date....

 

Thanks much

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hello,such filter already

    Hello,

    such filter already exists in MS Project, all versions: go to Project, Filter for, More filters

    then select "Should start / finish before"

    Alexandre

    Note: as I am working with MSP in French, the filter name might be slightly different.