Single line being printed on new page

Tony McClennonMember for 23 years 10 months
Created
2
5
0

Hi,

Another problem that has left me scratching my head!!

I have a schedule in MSP2003 that I want to fit onto two pages, but when I print it and set the page layout to print on 1 page wide x 2 high, it puts the final line onto a third page. If I try and set up for three pages, it still puts the final line onto a new fourth page, and so on.

I have checked that there is no page break before this last task, and have also tried manually scaling but without success.

Would be grateful if anyone else has experienced this problem and has found a solution.

Many thanks.

2 replies

Oldest first
  1. 0
    Lord Horn ·

    Alternatively, Try changing

    Alternatively,


    Try changing the paper size in the printer options.  Perhaps from A4 to Letter size.

     

    Almost all the times, this resolves the issue.

     

    Cheers,

    LH

  2. 0
    Tony McClennon ·

    Thanks - will give that

    Thanks - will give that suggestion a try.