Does anyone know how to make milestones that are not 100% complete but have a finish date that is in the past turn to red?

5 replies

Oldest first
  1. 0
    Kashif Khan ·

    Hi.In your case your program

    Hi.

    In your case your program is not updated and scheduled on milestone date, you need to update the activities on which this milestone was dependent on and after that when you will reschdule the program then the milestone will become 100%.

     

    regards

    kk

  2. 0
    Yvonne Stokes ·

    Thanks for the response but I

    Thanks for the response but I want to be able to show the task is running late and have it highlighted in red.

  3. 0
    Kashif Khan ·

    simple trick, right click on

    simple trick, right click on the milestone diamond and change its colour to red, though it is a manual trick but it will solve ur problem.

  4. 0
    Hlamalani Baloyi ·

    You right click on that

    You right click on that specific activity, you click on information,you go to the advanced tab,then on the bottom left you click to make that activity a milestone,

    Hope you find it helful

     

    Hlami

  5. 0
    Bo Johnsen ·

    Yvonne, A couple of initial

    Yvonne,

    A couple of initial remarks: 1) A milestone can only be 0% complete or 100% complete. Nothing in between. Milestone is defined as its duration and work being zero, so saying a milestone is 60% complete would just give the result 60% times zero which is still zero.

    2) Secondly, you can't have uncompleted activities/milestones in the past, however, many people still prefer to see the progress (zig-zag) line, so let's forget about that for a while.

    To answer your question you could make a formula for a flag field asking that if "Baseline Finish" is less than "Status Date" and "Actual Finish" equals "NA" then the flag field would turn "Yes" or something similar. Then make a red bar style incorporating that flag field. All bars for uncompleted activities that should have been completed according to the baseline will now automatically turn red.

    Regards,

    Bo   