MS Project 2007-Percentage of task in overall project.
In the Open Standard
Emerson SorianoMember for 15 years 7 months
- Created
- 4
- 4
0
Hi,
I don't know if this has been posted before but I can't see anything about it.
Without any assignments or progress, how do you get MS Project to show what percentage of each task is on overall project?
For example; one task is 10% of the project, next task being 60% & the last task is 30% - not as in completion.
If this makes any sense, can someone please help?
Many Thanks
Emerson
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?