Skip to content

Priority based levelling for split tasks having actuals

Proj2 Proj2Member for 14 years 7 months
Created
0
3
0

Hi,

I have seen below behaviour in 2007:
- A task A got split as there were some actuals before the start date followed by a work done on a different task
-Later there was a changing in project priorities with other project tasks getting higher priorities
- To make sure that half worked task A gets finished before any other task I set its priority to 1000
-Still pending part (after the split) of task A is prioritised after all the tasks having priority less to it! (I use Priority/Standard levelling; no splits allowed)

Why is that? To get around I had to delete actuals for Task A and then re-level.

thanks

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?