MSP2007 - Showing Progress within Summary Bar

Tony McClennonMember for 23 years 10 months
Created
3
5
0

I've seen a few posts on similar subjects on PP and through searching the internet, but not seen a reply that works for me (as yet!!).

When I used MSP2003, I could set up a "Summary Progress" bar that superimposed itself over the "Summary Bar".

However, when I try to do this in MSP2007, the progress bar gets hidden. I can show the progress bar if I set the bar shape so that it appears below the summary bar shape, but I cannot get it to appear on the same line which is our preferred option.

Not sure if MS have taken off the ability to do this, or I have completely lost the plot!!!

Any help gratefully received.

3 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Tony,it works exactly the

    Tony,

    it works exactly the same way in MSP 2007 as in MSP 2003

    be carefull to enter the same number in the "Row" column when setting up the Progress Bar on Summary Tasks; I presume you have 1 for Planned Summary and 2 for Progress Summary

    Alexandre

  2. 0
    Tony McClennon ·

    Alexandre, Thanks for

    Alexandre,

    Thanks for replying. Having had yet another look at the problem, it does seem as if it is related to one project file only - not sure why the Summary Progress will not show within the planned summary bar on this particular file, but having copied the entire content into a new file, it does now appear to be showing as I want it. Strange.....!!!!

  3. 0
    Alexandre Faulx-Briole ·

    Tony,when you copy the

    Tony,

    when you copy the project schedule from one mpp file to another, you only copy the tasks and resources, not the barts and filters setup

    therefore your new project is using the default setup you were missing in the first one

    Alexandre

Log in or join to reply