Prime Costs / Selling Price MS Project 2007
In the Open Standard
Remi SMember for 14 years 6 months
- Created
- 3
- 6
0
Hi all,
With Project 2007, I've entered all the resources / costs for the project, from the estimate. The amount shown in the column "cost" is the prime cost for each activity.
Now, I would like to apply a "mark-up" coefficient to each activity to obtain the selling price (the cost presented to our client) in another column if possible, using formulas, macros or MS project functions...
Does anybody know how to do this?
Many Thanks in Advance,
Regards,
RSa
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?