Pethanna RajendranMember for 14 years 7 months
Created
1
2
0

i wanna set alerts for important events in my schedule.

how to set alerts in MS project?

whether this can be linked to Outlook reminders?

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hello,there is no such alerts

    Hello,

    there is no such alerts in MS Project as in Primavera P6, I mean alerts that you will assign to WBS levels (summary tasks), or resources

    it is easy however to assign a "Deadline" to as task, and use this deadline as an alert:

    open the Task information dialog and go to Advanced, select the appropriate date for the Deadline;

    MS Project will display a new symbol in the Gantt Chart; as long as the scheduled finish date doies not exceed the deadline, nothing else is diplayed; when the scheduled finish date exceeds the deadline, a new red symbol shows up in the Flag (Blue uppercase I) column.

    I do not use Outlook, and cannot answer your 2nd question

    Alexandre