MS Project 2010 - Similar Software to Claim Digger for P3 or P6

Ronnel Anthony CelerioMember for 18 years 8 months
Created
3
4
0

Hi,

Good day Planners, Schedulers, Project Controls & the like. I would like to ask if anybody know if there is any software that we can use on MS Project 2010 for Schedule comparison, Just like the Claim Digger software to P3 or P6 Claim Digger Capabilities. Thank you.

Regards,

 

Ronnel Anthony Celerio

3 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Ronnel, MS Project 2010

    Ronnel, MS Project 2010 comes with a "Compare Project Version Utility" component, that you will add to the Ribbon This cannot be 100% compared to Claim Digger, but you can use it. Alexandre
  2. 0
    Ronnel Anthony Celerio ·

    Thank you Alex.. This is just

    Thank you Alex.. This is just what i needed to know.. Thanks again..

     

    Regards,

     

    Ronnel Anthony Celerio

  3. 0
    Burak Evrenosoglu ·

    You can also try Change

    You can also try Change Inspector.  It works with both MS Project and p6 xer files.  You can download a trial version at www.changeinspector.com