Dear All,

 

Is there a way to remove the outdent option while taking the print.My proejct manager want to show less gap in the task name column which is appearing because of the outdent option.I know there is option in P6 to remove this while we are taking the print..

please guide if this can be done in MSP also

 

thanks

4 replies

Oldest first
  1. 0
    Bo Johnsen ·

    Hi Kumar I'm not aware if

    Hi Kumar

     

    I'm not aware if there is such a function, but a quick solution to your problem is as follows:

    1) Insert a text user column, e.g. "Text1"

    2) Copy the entire "Task Name" column

    3) Paste in "Text1"

    4) Rename "Text1" as required

    5) Hide/move the original "Task Name" column so not visible when printing

    6) Print

     

    You could also make a formula in "Text1" so it automatically copied and updated the value of "Task Name", meaning you didn't have to think about copying and pasting every time you modified your programme.

     

    Regards,

    Bo

  2. 0
    Kumar S ·

    Hi Johnson..   thnaks a

    Hi Johnson..

     

    thnaks a lot.It worked...

     

    Rgds,

    Kumar s

  3. 0
    Alexandre Faulx-Briole ·

    Kumar,a much easier way to

    Kumar,

    a much easier way to do:

    1. in MS Project 2003/2007: go to Tools, Options, View, then unckeck the option "Indent name" at the bottom of the dialog box

    2. in MS Project 2010: the same option is available in the Quick Access Toolbar, "More Commands"

    Alexandre

  4. 0
    Kumar S ·

    Thanks Again

    Thanks Again