Schedule % Complete

Kumar SMember for 16 years 8 months
Created
2
2
0

Hello All,

Please guide me as i am new to MSP...

1) I have Prepared the schedule and set the baseline and updated the schedule for 1 week.

Now i want to show the Schedule % Complete Column Against the Actual % Complete.But i cannot find the Schedule % Column.Where i can get it.

2) For Showing the Actual % complete which of the % complete can be used as there are 3 types (% complete,Work % complete,Physical % Complete).

3) Is it neccesary to add resources to your project to monitor the Project or it can be done without resource assignment also.

Thanks in advance

Kumar S

2 replies

Oldest first
  1. 0
    Paul Harris ·

    The % Completes that MSP has

    The % Completes that MSP has are:

    • % Complet which is in actual fact % Duration
    • % Work Complete which may be unlinked from  % Complete
    • Physical % Complete which is a manually entered value.

    For any other you will need to enter a formulae ina custom column.

     

    Paul E Harris

    Eastwood Harris Pty Ltd, Melbourne, Australia

    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

    www.eh.com.au

    www.eastwoodharris.com

    www.primavera.com.au - a Primavera scheduling software resources site

  2. 0
    Kumar S ·

    Hello Sir,   thanks for ur

    Hello Sir,

     

    thanks for ur reply.

    Ok Then is there a way to get the Planned % complete week wise for my project from MSP.

    I have to show the week wise planned % of my project to my cleint one week before i start to monitor the project...
    In P6 I used to change the data date(Week wise) and get the planned % complete for that week.So is there anything like this which can be done in MSP also.