Hello All,
Please guide me as i am new to MSP...
1) I have Prepared the schedule and set the baseline and updated the schedule for 1 week.
Now i want to show the Schedule % Complete Column Against the Actual % Complete.But i cannot find the Schedule % Column.Where i can get it.
2) For Showing the Actual % complete which of the % complete can be used as there are 3 types (% complete,Work % complete,Physical % Complete).
3) Is it neccesary to add resources to your project to monitor the Project or it can be done without resource assignment also.
Thanks in advance
Kumar S