MS Project 2010 work units

Sandy MathesonMember for 22 years
Created
2
4
0

I am working a relatively simple schedule in MS Project but the clien wants me to show the work units in resiurce usage as days, not hours. Is that possible? And how?

Regards

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Sandy,not only possible, but

    Sandy,

    not only possible, but so straight away!

    File, Options, Schedule, "Work is entered in" ...

    Alexandre

  2. 0
    Sandy Matheson ·

    Many thanks!

    Many thanks!