MS Project Resource Allocation
In the Open Standard
Anand GudimanchiMember for 13 years 11 months
- Created
- 3
- 3
0
Dear Experts
Please can you guide me:
1. I had a PLANNED number of hours as 10 but the developer finished it in 5 hours ACTUAL. He is not overloaded
If I put in MPP, as task completed, I get overloaded figure to it's name. How can I resolve it.
Without baselining it.
2. I have assigned 4 developers to a project for 25% of time only for the said duration. How do we represent it so that
I don't have to manually put it the % allocation.
Thanks in Advance.
Anand