Skip to content

'Straightening the Progress Line'

Gordon FlemingMember for 13 years 11 months
Created
1
2
0

Looking for some help:

I am trying to ‘straighten the progress line’ in Microsoft Project.

I am looking to establish the projected end date of activities and projected end date of the project following the input of progress.

I have tried to use the following function but with no result:

Tools > Options > Calculation

  • Updating task status updated resource status
  • Move end of completed parts status date back to status date
  • And remove start of remaining parts back to status date
  • Move start of remaining parts before status date forward to status date
  • And move end of completed parts forward to status dates

Please Help.

 

Gordon.

1 reply

Oldest first
  1. 0
    Ismet Kocaman ·

    I hope I did not

    I hope I did not misunderstand your question. 

    Pls make sure the option "Split in-progress tasks" is checked (note that, Project does not split/move fixed-duration type tasks). If you have all the "Move end/And move" options checked (as mentioned in your post), Project aligns the progress with the status date as soon as you input some progress on the tasks. 

    Pls also see the following article:

    http://office.microsoft.com/en-us/project-help/specify-how-task-progress-is-shown-in-relation-to-the-status-date-HP043008259.aspx

    Regards,

    Ismet

    projectuser[at]fastmail.fm

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?