My updates in MSP is not showing the actual start date on Progress bars
- Created
- 0
- 5
Hi,
I am very new to the Microsoft Project 2010. Due to the conditions, I need to use the MS Project 2010 and I have not much idea about it. I have done the baseline program with resources. Now I want to monitor the status for this project. I did set the project as Baseline and start applying actual data to the individual items. Now my progress bars are not starting from the actual start date I am entering in as Actual start. For the items the % progress is more that what actually it should be, but still it doesn't show me early completion date for the items.
I really need your help to sort out this. Please help me.
Nilkamal
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?