I want to export the ressources distribution , from MS Projet into excel  in aim to plot the S curve .

Can any one tell me the  differents steps to configure the Projectexport-Assistant for this ?

Thanks

KAmel

1 reply

Oldest first
  1. 0
    Evgeny Z. ·

    Kamel,I normally go to

    Kamel,

    I normally go to resource usage view, select required data on the right side, copy it (Cntrl +C) and then paste it in Excel.

    I did not try to see, if it can be exported via report.

    Regards.

    Evgeny