Task Duration in Ms Project 2013

Mohammed ReehsabMember for 14 years
Created
3
3
0

Hi All,

         When adding a Task duration should we also include the no. of weekends also.

 

Regards,

Mahzaj 

3 replies

Oldest first
  1. 0
    Jack Black ·

    By default, Microsoft Project

    By default, Microsoft Project does NOT include weekends within the input Duration.  You can find more insight on Duration and Microsoft Project from here:

    http://www.pmconnection.com/modules.php?name=Web_Links&l_op=search&query=duration&orderby=hitsD

    Hope this helps!

  2. 0
    Mohammed Reehsab ·

    Dear Jack,               What

    Dear Jack,

                   What i would like to know is that when adding a task duration ie: no. of days  should we also include the holidays and weekends too.

     

    Regards,

    Mahzaj

     

     

     

  3. 0
    Mohammed Reehsab ·

    Dear Jack,               What

    Dear Jack,

                   What i would like to know is that when adding a task duration ie: no. of days  should we also include the holidays and weekends too.

     

    Regards,

    Mahzaj

     

     

     

Log in or join to reply