MS Project 2012 links between projects
- Created
- 1
- 3
I am normally using Primavera, but am curently in an organisation using MS Project 2012 (+server).
I have suggester to start link activities between projects, but the other planners in the org. claims, that MSP cannot handle this....!
Statement from Planners: "Generally when hard link is used while opening the plan or saving or publishing the master project will try to refresh the child projects with the updated data hence there is a performance issue in this type of linking. More over if the links are with big project the issue becomes more."
Do MS Project have a issue with links between projects? if so is there a workaround?