Schedule task based on resource availability
In the Open Standard
Satish KumarMember for 16 years 8 months
- Created
- 2
- 3
0
Hi,
I want to schedule a task based on the resource availability.
As per plan:
Project Start date is 02.06.2013
Piling Work Starts on 02.06.2013 by default, duration is 90 days, end date of piling is say, 01.09.2013
My resource , the piling rig will be mobilized by 03.09.2013. I have choosen the availability of resource from 03.09.2013 to 01.12.2013.
MSP Task Inspect informs that the task has to be rescheduled, when I click the reschedule button nothing is changing.
Pls Help.
Regards,
K. Satish Kumar