Microsoft Project Enterprise Edition
In the Open Standard
Liam DarcyMember for 22 years 8 months
- Created
- 0
- 2
0
Can i assign more than one coding to an activity in MSP, to enable me to view a filtered view for more than one field that the activity may fall under.
For example if i were to code an MCC installation as "Electrical works", would i be able to create another code library and assign a code to that same activity to filter all works for "Smiths Electrical" to see a filtered view of all the works done by Smiths?
Thanks in advance,
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?