Ms project - Actual cost column
In the Open Standard
Bala MuruganMember for 13 years 2 months
- Created
- 6
- 7
0
Hi all planners,
I am using ms project-2007 for my scheduling works. I have created a schedule with work resource,cost resource and did save baseline. Now i want to change the values in actual cost column of cost resource based on the site progress but when i tried to do so, i got a problem. When i increase the value of actual cost more than that of baseline cost , the duration of the particular activity is also changing.
I increased the actual cost because of more wastage of materials in the particular activity. I didn't spend more manpower or duration.
Is there a way to enter the actual cost without disturbing the duration of the activity?
What am i missing?
Thanks in advance.
Regards,
Ram
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?