Skip to content

Updating Schedule

Moutaz AldeibMember for 22 years 9 months
Created
3
4
0

Dear Planners,

How to update schedule in MSP, I mean whatever the percentage you enter for tasks, the completion date is not changed anymore, not like Primavera?

Regards,

Moutaz

3 replies

Oldest first
  1. 0
    Li Qian ·

    I can share some ways that I

    I can share some ways that I always use . i am a new guy to MSP,but you can have a try.

    after you typing into the percentage in the complete coloum , you can add another coloum called "remain duration", and type into you estimated remain duration. the finish date will change. 

  2. 0
    Moutaz Aldeib ·

    Thanks Li,This way is

    Thanks Li,

    This way is manually updated, it does not make sense, what I need is; the schedule should be automatically updated once the actual dates and percentage complete are entered.

    Regards,

    Moutaz

  3. 0
    Hamid Hasanzadeh ·

    Dear planners,I rescheduled

    Dear planners,

    I rescheduled my project, the new finish time change when I update project. how can I update rescheduled project in MSP?

     

     Best regards,

    hasanzadeh

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?