Calenders

Dan MårtenssonMember for 12 years 3 months
Created
3
2
0

Hi all,

 

I´m sitting on a concern that I hope you can help me with.

 

I have diffrent work packages that need diffrent calenders. I creat the calenders of the various jobs that exist.

What happens is that if I plan more then 8 hours a day so shortened duration down and make my activity shorter. I want to add 10 days, but the pace of work at 12 hours a day.

 

How can I do this?

 

Greatful for a quick reply

 

Regards

 

Dan

3 replies

Oldest first
  1. 0
    Dan Mårtensson ·

    Anyone? /Dan

    Anyone?

     

    /Dan

  2. 0
    Evgeny Z. ·

    Dan,you need to create a

    Dan,

    you need to create a seporate calendar and assign it to this spesific task:

    See the link below:

    http://office.microsoft.com/en-gb/project-help/set-working-times-vacations-and-holidays-for-your-project-HA001224299.aspx

    Consider also Task option "Scheduling ignors resource calendar"

    Regards.

  3. 0
    Dan Mårtensson ·

    Thank you! The problem got

    Thank you!

     

    The problem got slowed yesterday

     

    /Dan