MS PROJECT UPDATING TASKS
- Created
- 3
- 4
Hi everybody, I have a question about MS Project.
I have a task that starts on 16.04.2014 and finishes on 26.06.2014.
Start: 16.04.2014
Finish: 26.06.2014
Progress Data’s:
Actual start: 29.04.2014
Status Date: 29.06.2014
Completion: %60 (Actual Start till Status Date)
So in my opinion, I did %60 in 60 days, so I should work for 40 more days to complete task. The finish date should automatically change to “29.06.2014+40 days”. There should be only one bar in gantt chart that shows completed task between actual-status date and not-completed task for 40 days.
I tried all update tasks procedures but I couldn’t manage.
I just want to make this calculation automatically in MS Project.
What should I do? What are your recommendations?
3 replies