MS Project 2007 - Remaining Work

Matthew RamsdaleMember for 13 years 11 months
Created
0
3
0

Hi, relatively new to using Microsoft Project 2007 and looking for some knowledge.

I have created my schedule, resourced and generated my man hours (work). I have used the baseline man hours, extracted from the task usage sheet, to generate a baseline S Curve on a Earned Man Hours week by week basis. I have now entered progress into the schedule and due to delays with access etc we are behind schedule. I know what we have earned for so I can enter this into the S Curve also.

The problem I am having is seeing the effect the delays have had on the remaining work. Does MS Project reallocate remaining man hours across remaining duration, based on resource and can you show this in the task usage screen? I am wanting to use this to generate the forecast to completion.

If not, how do I extract this info from the schedule.

NOTE: The schedule is not cost loaded.

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?